Skip to content
The title slide and first slides of the Monthly Board Project Update Slides template

Monthly Board Project Update Slides

Presentation template for Google Slides and PowerPoint

Make a copy in Google Slides
Price
Free
Slides
12
Difficulty
Beginner
Updated
November 12, 2026

Every slide (12)

Overview

Board members rarely have time for a full status pack, so the headline has to answer three questions: is the work on schedule, is the money on plan, and what could still go wrong. This deck keeps to those three areas and puts any decision the board must make near the front. Each slide states a figure, a status and an owner, so the sponsor can see at a glance what changed since last month.

The sample reports Project Lantern at Vesperly Group, a fictional organization, with 58% complete, a $3.2M baseline, a forecast at completion 3.1% over budget and one decision on a $100K overrun. It includes a KPI scorecard, a spend curve, cost categories, a risk table and four actions. Replace the project, figures and owners with your own, and write your RAG thresholds into the key before the first board pack.

Useful for

  • A sponsor preparing the monthly pack for a board meeting on Thursday
  • A PMO analyst checking budget burn against the forecast at completion
  • A delivery lead listing the risks and actions they own before steering group

What's included

  • Progress: headline stats and a KPI scorecard with target and status per row
  • Burn rate: a cumulative spend chart against the planned curve, with insights
  • Money: forecast at completion, contingency left and the cost overrun chart
  • Decision: one box for the board decision, with the reason and the deadline
  • Risk: a table of top risks with owners, ratings and responses, plus actions
  • Make it yours: five steps to replace the sample project with your own

How to use it

  1. 1

    Click Make a copy in Google Slides, then confirm on the Google page. The copy is saved to your own Google Drive.

  2. 2

    Replace the project name, sponsor and reporting period on the cover slide.

  3. 3

    Set the RAG thresholds in the key, then rate each row against them honestly.

  4. 4

    Update the milestone dates, budget and forecast with your current baseline.

  5. 5

    Delete the guide slide, then share the deck with the board pack or present it at the meeting.

What you need

Requirements

  • A Google account with access to Google Slides

Works with

  • Google Slides
  • Microsoft PowerPoint (File → Download → .pptx)

Questions

Are the company and project real?

No. Vesperly Group, Project Lantern, the sponsor and every budget and milestone figure are fictional sample data, so replace them with your own before the board sees the deck.

What should a red status mean?

Define it in the key before you report. A common rule is red when a milestone is more than two weeks late or the forecast is outside tolerance, but your PMO should set the thresholds and apply them to every project.

Why show forecast at completion?

Spend to date says how much has gone out, not whether the project will finish within budget. The forecast at completion adds the cost still to come, so the board can see the final number and the margin left.

  • #project-status-report
  • #board-project-update
  • #rag-status-report
  • #steering-committee-report
  • #project-status-slides
  • #monthly-project-update
  • #budget-forecast-report
  • #project-risk-register

More project status report templates

See all 14

Also in Project management

All project management templates
Get this template

Preparing your template…